The Incident

We received a $366,000 TP recovery claim on this earthmoving equipment which had reportedly suffered a lightning strike event. We were instructed by a legal firm to provide an expert report on the incident, damage and confirmed costs.

Our Findings

A comprehensive inspection with an ARC Assessing Equipment Specialist

After completing our due diligence, we clearly showed there was no evidence to prove the event as described had happened. We presented a list of 12 questions for clarification to the TP insurer and their appointed assessing provider.

When the TP insurer and assessing provider failed to answer any questions after a 3-month period and following instruction from the legal team, we adjusted the presented costs to a fair and reasonable settlement recommendation of $125,000 net of GST.

As this claim came to us as a TP recovery claim with minimal information, the challenge was to identify all relevant missing information, discuss all aspects of it with the legal team in a way they understand and then provide a fair and reasonable report that clearly illustrates that all variables have been considered.

We provided recommendations around 3 different areas of the repair:
1. Components likely to be damaged
2. Components possibly damaged
3. Components not likely damaged as a result of the described event.

The Result

On a fair and reasonable basis we provided a recommendation based on paying for all components likely damaged and all components possibly damaged and presented a claim settlement recommendation in the amount of $125,000 net GST. We believe our recommendation has been accepted by all parties.

If you would like to experience the results the ARC team of equipment experts can provide – don’t hesitate to give us a call on 1300 280 141 or send us an email at claims@arcassessing.com.au.

Tags: 

You can also read

Caterpillar Dozer Case Study

We received a $366,000 TP recovery claim on this earthmoving equipment which had reportedly suffered a lightning strike event.

John Deere Boomspray Case Study

The repair estimate received with this lightning strike claim, due to a severe weather event, was just over $130,000.

JCB 542-70 Telehandler Case Study

We received a claim on this unit which had suffered an operator error event, resulting in impact damage to its cabin and boom.

1300 280 141claims@arcassessing.com.au
Unit 5, 14 Merino Entrance, Cockburn Central WA 6164
© 2023 ARC Assessing Pty Ltd (ABN 39 163 011 550)
linkedin facebook pinterest youtube rss twitter instagram facebook-blank rss-blank linkedin-blank pinterest youtube twitter instagram